Current Events
CLOVERDALE PUBLIC SCHOOLS PROJECT
Cloverdale Public Schools recognized the need for independent
representation and began seeking out services that would protect their best
interest. Late 2007, Kramer was hired to assist Cloverdale Public Schools in
maintaining control of their project. The following is a brief history of significant
issues leading to the successful kickoff of construction activity 3/5/08:
- Kramer recommended that the entire project be bid
as (8) separate packages (as alternates) under a unified base bid. This effort
would ultimately offer the following viable results:
- (6) qualified bidders
- (6) competitive bids
- THE PROCESS CLEARLY DEMONSTRATED NO
PREMIUM MARK-UP (BY THE GC) FOR ACCEPTANCE OF (1) PACKAGE OR ALL (8) PACKAGES.
THIS AGAIN, SIGNIFICANTLY DIMINISHES THE VALUE CONSTRUCTION
MANAGEMENT OFFERS TO THE PROJECT PROCESS (especially for
projects under twenty million dollars). IN FACT, CONSTRUCTION
MANAGEMENT WOULD HAVE ADDED SIGNIFICANT COST TO THIS PROJECT.
- Kramer also recommended the addition of (2) other
key alternates that saved the client as much as $21,000. Accepting these
key alternates also significantly strengthened project control over the
contractor.
- The separate alternate packages also allowed the
client options to move forward with the project and remain under budget
without entering into costly value engineering.
** Update **
August 2008 – Project is on
schedule under budget and Kramer is reporting a cost savings of +$100k. AN
ESTIMATED 500% RETURN ON INVESTMENT OF KRAMER SERVICES.
Daniel M. Sulkoske, Agent to the Client
Telephone:
(317) 858- 9113
Fax:
(317) 858-9111
|
Address:
474 Southpoint Circle
BROWNSBURG, IN 46112
Mailing address: P.O. Box 1018 - Brownsburg, IN 46112-5018
|
Email:
dsulk@kramercorporation.com
|
© Kramer Companies
2008
|